Dr. Oetker Tiefkuehlprodukte KG Wittlich
New Construction of a Logistics Centre
Dr. Oetker Tiefkuehlprodukte KG Wittlich
Wittlich/Germany
Axel Peske, Civil Engineer
Architect Stefanie Joost, Civil Engineer
Martin Thiele, Civil Engineer
Project Management, Building Planning
2007
12.500 (New Construction)
For a further extension phase of the expansion of the existing storage area the task consisted of creating the maximum storage capacity with the annexed commissioning, disposal and dispatching areas on the remaining plant area.
An apparently simple planning becomes an extremely interesting task
With the size of the planned building the limits of fire protection were reached. By means of purposeful planning this problem was solved with the appropriate arrangement of complex dividing walls. The integration of a highly technological conveyor technique was also taken into account in the general planning.
Simultaneously, the necessity became apparent of integrating an office and administration building as a separate construction into the existing work structure. Here, we succeeded in planning the building in such a way that the modular extension possibility of the adjacent work areas was not affected.